Thank you, Madam Chair. I just want to add my voice to the comments that have already been made by Mr. Bromley and Mr. Dolynny. I, too, have been waiting for some comprehensive renovations at Stanton and we’re still waiting, so I just want to add my voice of discontent to those of my colleagues’.
I have one question with regard to the planning study. As advised, this was a $5 million budget and we are carrying over almost $2.2 million, which suggests that it’s getting there. It’s maybe 60 percent done. But I’d like to know from the Minister when this planning study is expected to be finished. He’s advised us that there’s going to be money in the next capital budget for this particular project, but is it going to be a situation of a planning study not being done until the end of this fiscal year and we’re then carrying over the $20 million because we’re not ready to go to any, you know, to further the project? When is this planning study going to be done?