Mr. Speaker, originally this project was slated for completion for March 31, 2013, but as the Member knows, because he lives in Inuvik and he has seen the school which is still standing, we didn’t finish on March 31, 2013. The new date is June 20, 2013. That is when we expect the school to be done, the site to be open.
The reason it was delayed is because ceiling tiles and fume hoods not identified in the original Hazmat were identified during Hazmat deconstruction. There is asbestos in the drywall that wasn’t identified in the original Hazmat assessment and mudded pipe joints which contain asbestos were also not in the pipes. We had to get those things out of the school before we could move forward with the actual teardown. Thank you, Mr. Speaker.