Thank you, Madam Chair. Just so that I can get to proper closure of this file, during the demolition phase there was definite anticipation that there was going to be a significant amount of asbestos and contaminated materials. I was led to believe that there was more contaminated material than earlier, I guess, thought of when the demolition commenced and even during the different phases of the demolition process.
My question is that given the budget that we had of the $8.6 million, did that cover all the extra anticipated disposal of asbestos and any other contaminated substances that were known during the demolition phase?