Mr. Speaker, the Member is quite correct. The Public Utilities Board, PUB, did not approve the Northwest Territories Power Corporation’s interim rate application that was to have come into effect on June 1st. NTPC will reapply for an interim rate, the same 4.8 per cent increase when it submits it GRA later this month with an anticipated effective date of August 1st, 2016. So we’re not anticipating much loss or any loss of money in a significant amount.
Louis Sebert on Question 257-18(2):northwest Territories Power Corporation Interim Rate Application
In the Legislative Assembly on June 17th, 2016. See this statement in context.
Question 257-18(2):northwest Territories Power Corporation Interim Rate Application
Oral questions
June 16th, 2016
See context to find out what was said next.