First of all, the project is currently undergoing an environmental assessment by the Mackenzie Valley Environmental Impact Review Board. That was submitted or it was referred to an assessment in, if I remember correctly, end of July of 2016.
As we move forward and it works through that process, the next part of it was that we actually release the request for proposal to get assistance in developing the procurement documents for this project. Moving on from there, the next step will be going out to an RFQ process to see to get qualified bidders who can handle this project, the building of it and the financing of it. From there, we'll move to an RFP process and, from there, hopefully into construction. So I hope that answers the Member's question.