Thank you, Mr. Speaker. The contractors are working out there right now. They have 3.5 kilometres of embankment that they had to finish in the centre section of the highway. With that work, there are roughly 147,000 cubic metres of material that will be put in place to finish up those 3.5 kilometres. They had eight culverts to finish up, and two bridges, and all that work is nearing completion this winter. Moving on into the summer, operations have surfacing gravel, which will include crushing, stockpiling, and laying out the gravel, then finishing up the guard rails, signage, and such for the final touches. Thank you, Mr. Speaker.
Wally Schumann on Question 719-18(2): Inuvik To Tuktoyaktuk Highway
In the Legislative Assembly on March 9th, 2017. See this statement in context.
Question 719-18(2): Inuvik To Tuktoyaktuk Highway
Oral Questions
March 8th, 2017
See context to find out what was said next.