Just one final question. I mean It seems to me that there will be some degree of loss here, and it is going to be significant. There is no small number involved in this. This is very important. Either taxpayers or ratepayers, one or the other, are going to probably end up having to pay. Is the Power Corporation at least starting to plan and take next steps as it relates to how they will recover some of these lost costs?
Cory Vanthuyne on Question 913-18(2): New Generators For Yellowknife Power Plant
In the Legislative Assembly on September 28th, 2017. See this statement in context.
Question 913-18(2): New Generators For Yellowknife Power Plant
Oral Questions
September 27th, 2017
See context to find out what was said next.