Thank you, Madam Chair. So as the Minister mentioned, for the Whati T-line next year, we're doing some work with the Tlicho government right now on the routing for that project and hope to be available to advance that to a decision point of whether we pursue federal funding for that project.
In Gameti, we've been looking at a mini hydro study there. We did update some pre-feasibility work in June of this year. And it does look like there is sufficient water available to meet the community power needs.
So in terms of our planned work for next fiscal year, we're going to continue with some of the technical studies in the planning and move that forward -- that project forward in conjunction with the Tlicho government. Thank you, Madam Chair.