Thank you, Mr. Chair. Mr. Chair, in regards to the Mackenzie Valley Highway, maybe perhaps I'll start with that project.
So we are still on track for 2022 developer assessment DAR submission. We are looking at -- you know, there's a lot of work that's involved in order to put the -- the regulatory process in place, and so we are still on target with that. Let me just see what we are at for the...
So the department is working to develop some of the work plans to collect some of the environmental work on the engineering baseline data, and it is focused on advancing engagement with Indigenous groups as well. So on target for the SGP, and we hope to undertake some geotech and environmental and also Indigenous knowledge gathering this year. Thank you, Mr. Chair.