Thank you, Mr. Speaker. The Whati Transmission Line is a key initiative, and I'm going to keep saying this, under our 2030 Energy Strategy. This proposed project will occur 100 percent on Tlicho lands, and the GNWT and the Tlicho governments are committed to advancing this important project together.
The Department of Infrastructure and the Tlicho government recently began working together to be able to determine an acceptable routing corridor for the transmission line between the Snare Forks hydroelectricity facility and Whati. The tentative date for the completion of this part of the work is in fall of 2022. Once this routing corridor for the project is known, infrastructure and Tlicho will collaborate on preliminary engineering and design. This work will include internal preliminary capital costs estimates that reflects the design work and the routing corridor. Thank you, Mr. Speaker.