Thank you, Mr. Speaker. Mr. Speaker, to date, the GNWT's only calculated the liability required to carry out the order issued by ROGO. This order includes closure of oil and gas wells at Cameron Hills along with removal of pipelines and related infrastructure such as tanks and batteries. The cost of reclamation under the land use permit and water license, such as sumps and contaminated soil, has not been estimated at this time, Mr. Speaker. Thank you.