Thank you, Mr. Speaker. And I thank the Member for the question. This site did go through a modern regulatory process, Mr. Speaker. Unfortunately, the funds held transferred to the GNWT and OROGO at devolution were insufficient to cover the liabilities. The GNWT is currently carrying out the regulatory and policy work set out in the work plan to implement the GNWT's approach to contaminated sites and management. Some of this work has been completed and the remaining work is ongoing. So, Mr. Speaker, we're going through a process. We're trying to get it done. And, again, we don't know what the true costs are going to be until all the work is done. Thank you, Mr. Speaker.
Shane Thompson on Question 1372-19(2): Cameron Hills Gas Field Enviromental Liabilities
In the Legislative Assembly on February 14th, 2023. See this statement in context.
Question 1372-19(2): Cameron Hills Gas Field Enviromental Liabilities
Oral Questions
February 14th, 2023
Page 5272
See context to find out what was said next.