Thank you, Madam Chair. So for the runway project, things are progressing on time and on the adjusted budget. We recently signed the contract for, I think, about $82 million to continue the airports and all that work would take us up to completion of the runway except for electrical and paving. I think that will take us about another year and a half, I do believe.
In terms of the airport terminal building, so that project is currently under negotiations, so. The proponent did submit a bid. We're working through that bid right now, and that work continues. Thank you, Madam Chair.