Thank you, Mr. Speaker. In terms of the Tulita housing delivery, the modular units for Tulita are being provided by two contractual agreements, each with NWT-based manufacturers. Four units, again, we talked about this earlier in session, are manufactured in Fort Good Hope with the K'ahsho Got'ine Trade Centre with units -- with plans to bring the units to the community on the 2028 winter road. The remaining six units will be manufactured in Hay River by Metcan Building Solutions, an Indigenous-owned business. These units will be delivered to Tulita on the 2027 winter road with the 2027 barge as a contingency plan. Thank you, Mr. Speaker.
Lucy Kuptana on Question 1279-20(1): Delivery of Housing Units to Tulita
In the Legislative Assembly on June 3rd, 2026. See this statement in context.
Question 1279-20(1): Delivery of Housing Units to Tulita
Oral Questions
June 3rd, 2026
See context to find out what was said next.