Thank you, Mr. Chairman. I think one of the major concerns we had in the standing committee on finance was that most of us had thought that the total cost of the Legislative Assembly building was going to be covered by the bond issue. Apparently much of this $10 million that we are looking at in total expenditures over the next two or three years was in other departments' budgets up until this year, and there was a decision made to move everything and show it as one budget item.
It caused us an awful lot of concern, and I guess the public really never seemed to understand that this whole thing would be covered by the bond issue. I know I did not know that.
The question for the Minister is, can we be certain that we have a fairly accurate forecast as to what the total cost will be for this project when we see the $10.044 million as total capital projections; on a scale of accuracy, how accurate does he believe this projection is?