Thank you, Mr. Chairman. We can share this information, but I can just indicate the consultant’s design and inspection: $6.485 million; Public Works expenditures -- travel, commissioning, insurance, small contracts, course of construction: $700,000; relocating client expenditures, relocating existing building and furnishing and move in: $1.845 million; Dowland Construction Limited contract, phase two: $92.3 million; drainage and site preparation: $2.335 million; and, there’s an $11.7 million contingency, for a total of $115.365 million.