Thank you, Mr. Chairman. In order to maybe try to provide clarity, if I could just point out the information that we have, the existing base budget for the Charlotte Vehus was $842,000. They put out a bid for a contract that came in at $1.459 million. That contract was awarded. The amount of money they had in that program area, $842,000, a gap of $547,000 that has been recognized as a base deficiency, and we are here to seek funding. Currently, there has been an adjustment to 2013-2014. Up until now the authority has been absorbing that cost and running a deficit which is no longer sustainable. The contract amounts have been fairly consistent. This is not a case where there was a contract awarded for $842,000 and the price was subsequently recognized to be inadequate on the contractor’s part. It was just the
funding in the organization wasn’t there to cover that $1.459 million.