Thank you, Mr. Chair. The Member is correct; there were sections of the line that floated to the surface once the ground melted. The line has been checked from one end to the other and they have identified all the areas and they have worked to ensure that the cable is properly buried. Given that is was a unique sort of process, it was something that wasn’t anticipated but has been rectified at the cost to the contractor. There is a plan that has been put into place over the summer to do that. Thank you.