This is page numbers 2503 – 2544 of the Hansard for the 17th Assembly, 4th Session. The original version can be accessed on the Legislative Assembly's website or by contacting the Legislative Assembly Library. The word of the day was million.

Topics

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

The Chair

The Chair Jane Groenewegen

Thank you, Mr. Bouchard. Mr. Neudorf.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Russ Neudorf

Thank you, Madam Chair. Yes, we have gravel sources identified for the construction of the highway. Last winter we had gone and done quite a significant investigation and found the material required to construct the subgrade. We would like to carry that on to drill holes, do some more geotechnical investigation for some additional sources that are on the remainder of the route. With that information we will be able to go and finalize the design, so take it from an 85 percent to a 100 percent design. The geotechnical will also let us investigate bridge locations so we can finalize the design on the bridges as well.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Robert Bouchard

Robert Bouchard Hay River North

I’m looking at this supplement here for $5 million, and there only being several weeks left in the fiscal budget of the territorial government, I’m just wondering how the department expects to be able to spend this money on the upgrade to the 177 access road.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Russ Neudorf

There has been much interest expressed by the contractors in the region to get work underway. The leaders in the region have asked us to get work underway as quick as we can. The last missing piece, and part of that was to get the letter from the federal government, and so we are here to seek this $5 million in additional funding for this year. We have been talking with contractors who are ready and willing to get that work underway as soon as the funding is approved.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Robert Bouchard

Robert Bouchard Hay River North

My next question is concerning we’ve been given some information from the federal government that they’re funding most of this project. I’m just wondering where the federal government sits on any cost overruns. Is that the responsibility of the GNWT?

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

The Chair

The Chair Jane Groenewegen

Thank you, Mr. Bouchard. Mr. Miltenberger.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Michael Miltenberger

Michael Miltenberger Thebacha

Yes, Madam Chair, we have a contingency built into the project, but clearly the cost overruns would be the responsibility of the Government of the Northwest Territories. Thank you.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Robert Bouchard

Robert Bouchard Hay River North

I realize that some of these are specific to the whole project, but my feeling is that the $5 million commitment here is kind of a tipping point if we go forward with this. I think we should be supportive of the whole project.

I guess my question is for the contracting out of this work and more to follow. Does the government expect contractors to carry bonding to complete this project?

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

The Chair

The Chair Jane Groenewegen

Thank you, Mr. Bouchard. Mr. Neudorf.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Russ Neudorf

Thank you, Madam Chair. We have not yet determined the final approach to procuring the construction work, but all government contracting procedures, rules and regulations would be followed as part of that. Thank you, Madam Chair.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Robert Bouchard

Robert Bouchard Hay River North

The deputy minister kind of led me into my next question. I’m just wondering how the GNWT expect… We talk about the economic development, the opportunity this provides for our members in our communities and our constituents in the Far North. I’m just wondering how the department expects to maximize the northern content for the employment on this project.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

The Chair

The Chair Jane Groenewegen

Thank you, Mr. Bouchard. Mr. Miltenberger. Oh, you’ll refer to Mr. Ramsay. Mr. Ramsay.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

David Ramsay

David Ramsay Kam Lake

Thank you, Madam Chair. If the Member could repeat the question for me, please.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Robert Bouchard

Robert Bouchard Hay River North

I was just asking about the procurement of the work and how the government expects to maximize northern content and northern employment. We’re talking about this as an economic development driver. How is the department expecting to maximize the fact that the Northwest Territories is going to see the full impact of this $299 million project?

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

David Ramsay

David Ramsay Kam Lake

Madam Chair, that would be in how we procure the services to build the highway. There are companies located in the Beaufort-Delta that could carry out the work. Our government’s perspective on this has and will

continue to be that opportunities have to be maximized, not only in the territory but in the region itself. In procuring the project, we will make every effort to ensure that as much of that $299 million stays here in the Northwest Territories, and specifically in the Beaufort-Delta. Thank you.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Robert Bouchard

Robert Bouchard Hay River North

As I indicated earlier, I think the $5 million we’re approving here is one piece of the large puzzle, and I think we’ll be seeing further supplements here quickly. Basically to the point of committing to the project, I think this is a tough decision for a lot of the Members here to decide what we want to do with this money and whether we support this project. For me personally, it’s been a challenge back and forth. I know it’s large infrastructure money, and it’s hard not to look at last projects such as the Deh Cho Bridge and the overruns there. The Deh Cho Bridge had a revenue stream to it, but this one has a revenue stream and the federal government sponsoring basically two-thirds of it, from what the numbers are indicating.

I see the benefit to the area, the economic development driver, and I’m supportive of that. I guess from my community, we’re interested. We were always interested in seeing expansion of the Mackenzie Valley Highway basically from the south, maybe Norman Wells where there’s a lot of activity where we’re seeing the benefits. But I understand the federal government’s committed right now to the north end and their nation building and us building a territory that’s going to have a road all the way to Tuktoyaktuk, to the other ocean.

So I’m supportive of this $5 million, and I’m supportive of the entire project. It’s been an ongoing debate and discussion in our community. We’ve had discussions whether we support the project or not, and I think we need to look at all the options. The federal government increased their borrowing limit; they made it accessible for us to do this. So I am giving my support to this project, I guess.

I know there are lots of questions and lots of concerns from different Members, and I think we need to challenge the Cabinet and the Premier to make sure certain things are being done, that this is not just being an open chequebook to build the road and do a whole bunch of cost overruns. I think we need to make sure that we stay on budget and we make sure the road is built to a good standard.

I know there are all kinds of questions out there, and there are questions and concerns whether we have a complete design or not. But some of these projects are hard to do unless you start going into them. I’m hoping that things will get done more efficiently, and I hope the number for one rare reason would be under budget, which I know the government definitely doesn’t have a good track record of keeping projects under budget.

That being said, I think the area needs our support, and I think it is building a nation, building a territory, and I think it’s the first leg in building the Mackenzie Valley Highway. We look forward to probably the south end. My colleague to my right here from the Sahtu and I would like to see that come to fruition in our terms of offices here, at least to have something to move the project forward.

That being said, I just wanted to lend my support to the project at this time. I know there are lots of questions out there, and we’ll have to deal with those questions and those concerns as we move forward. Thank you, Mr. Chair.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

The Chair

The Chair Jane Groenewegen

Thank you, Mr. Bouchard. Anything in response? Okay, nothing. That was a comment more than anything else. Thank you, Mr. Bouchard. We are still on page 5 of the 2012-2013 Supplementary Appropriation (Infrastructure Expenditures) No. 3. Next I have Ms. Bisaro.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Wendy Bisaro

Wendy Bisaro Frame Lake

Thanks, Madam Chair. I have specific concerns about the only one project on this page, and that’s the Tuk-Inuvik highway. I think certainly Members and the Regular Members, through our discussions, know that I have a lot of concerns with this project. But I’ll ask a couple of questions here and perhaps give my editorial later on.

I heard the Minister say a little bit earlier in response to another Member that, I think the question was, when is enough enough? The Minister said enough is enough when we’re opening the road. I thought to myself, that’s all well and good, but at what price? Where is the Minister and this government willing to sign off on this project? We’re, at the moment, hoping it’s going to be $299 million plus what we’ve spent already. So that puts us up around $312 million or so, plus maybe $30 million in unknown risks. So we’re up around $350 million, give or take. So should we encounter other difficulties along the way, at what point does this government think enough is enough? Thank you.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

The Chair

The Chair Jane Groenewegen

Thank you. It’s a hypothetical question, but I’m going to ask Mr. Miltenberger to respond.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Michael Miltenberger

Michael Miltenberger Thebacha

Thank you, Madam Chair. It is truly a hypothetical question. The fact of what we know is we have $299 million: $200 million just confirmed from the federal government and $99 million out of our own pockets. We have some costs already of $12 million.

We’ve given every commitment we can possibly give at this juncture about managing the project. We have a contingency fund. We’re going to do all the work up front to be ready for construction this coming fall. So it’s on that basis that we’re proceeding. Otherwise, if we took the approach

suggested by the Member, we could potentially paralyze ourselves as a government on just about everything, all the potential what-ifs if everything goes bad and nothing works.

So we’re proceeding on the $299 million, and we’re going to have every confidence. The Minister of Transportation has articulated that repeatedly, that we will do this and we’ll do it right and we’ll do it on budget. Thank you.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Wendy Bisaro

Wendy Bisaro Frame Lake

Does the Minister want to guarantee that, on budget? Rhetorical question. Thanks.

So one of the other statements that was made, by either the Minister or the deputy minister, was that geotechnicals will be finalized in the coming months and that’s one of the unknowns for me, and I think it’s one of the unknowns at the moment for the department and for the project. So I haven’t heard it said, in terms of geotechnical, there are concerns from certain Members that the terrain that we’re working in can be very difficult, we’re dealing with permafrost and I’ve heard it said that we are dealing with a certain section of the road we’re dealing with a glacier. So if we don’t yet know, we haven’t finished the geotechnical, how can we be as certain as we are about the cost of the project? Thank you.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Michael Miltenberger

Michael Miltenberger Thebacha

Thank you. There are no glaciers up there that I’m aware of. The reason we know what we do is because we’ve taken the time and we’ve spent some good, wisely invested money up front to do the estimating. We’ve started way back, many years ago, with a very rough estimate, and we’ve finalized it and fine-tuned it to the point where we came forward with confidence that we could do it for $299 million. So we spent $12 million getting ready to make that determination.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Wendy Bisaro

Wendy Bisaro Frame Lake

Thanks to the Minister. So, I mean, we’re working on a best guess, and I guess that with any project we’re working on a best guess, but it doesn’t give me much comfort at this point, unfortunately. It’s been mentioned several times already that we have been given, so to speak, $200 million from the federal government, and that’s a huge amount of money. I certainly appreciate the commitment of the federal government to the project. However, it’s my belief, and I believe it’s practiced elsewhere, that new roads are 100 percent paid for by the federal government and we are now getting 67 percent, approximately, of our project covered by the federal government. I’m having a very difficult time with the reduction. We were talking about a 75/25 split. I was relatively okay with a 75/25 split, but now we’re down to 67 percent and that just means that’s a greater burden on us, as a government, and it concerns me a great deal. It concerns me on two fronts, one, that we have to put more money in of our own and secondly, that the federal government, in my mind,

is backing away even further from their responsibility to pay for new roads across our land.

So I’d like to know, several Members have been talking about investment and that it’s economic development and so on, and it’s been referred to by a couple of people as a long-term investment. I’m having great difficulty understanding and believing, in my heart, that this is a long-term investment. I see the Mackenzie Valley fibre optic link as a long-term investment because it will grow businesses in the Beau-Del, and it will grow businesses and it will grow employment for people up there for a very long time. I see this project as not necessarily growing businesses, but it certainly will employ people, but only for a five-year period. So I don’t see this as a long-term investment. Could the Minister explain to me how this could be characterized as a long-term investment project? Thank you.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Michael Miltenberger

Michael Miltenberger Thebacha

Thank you. We make long-term investments in the territory, that’s what we do as a government. Seventeen Assemblies have been working, Assembly after Assembly, to put infrastructure in the ground, on the ground that improves the quality of life that helps build the territory that we all agreed is part of our vision. Part of that critical infrastructure is roads. A road, the northernmost section of the Mackenzie Highway has been a critical part of the northern dream for longer than I can remember. So if the Member is asking if we look around the North for every dollar we spend, where do we get our money back, where is the economic return on our investment, then we would have a very interesting, challenging discussion, because we make political decisions in our political self-interests that may not have that immediate return on the dollar. But if you look, over time, the value of a road that opens up the northernmost part of the territory, I believe the Member’s comments are prefaced on the assumption that somehow there will never be any further activity up in the Mackenzie Delta, the Beaufort-Delta, when we know it’s sitting on a storehouse of resources. What we invest today, I believe, over time, will prove its value the same as the bridge will. There’s no longer people complaining about the bridge, except maybe politically about the process, but nobody talks about gosh, I really miss the days of the ferry and the winter road and all the uncertainty and not being able to travel 24/7 and, man, those were the good old days that I really long for.

So this is, I think, a territory-building, nation-building investment. It is going to have economic impact far beyond the term of this Assembly. Thank you.

Consideration in Committee of the Whole of Bills and Other Matters
Consideration in Committee of the Whole of Bills and Other Matters

Wendy Bisaro

Wendy Bisaro Frame Lake

Thanks. Just one last question. How many people are required to construct this road? How many PYs are going to employed over this five-year project? Thank you.