Thank you, Mr. Chairman. This is quite a bit clearer to me than before. In 1990-91, the Member is correct in that there was money allocated for this project. In 1991 the department went out to tender for design. The department was told that this design was going to be too expensive. In 1991-92, the department had, in their budget, $400,000 of which $115,000 was spent on a design that would allow them to build an applied arts building and library that would be less expensive than previously designed. In 1991-92, the design was not able to be completed, and we are saying that on the design year of 1992-93, we cannot build the building since we have not finished the design that would allow us to build the facility.
What we are saying, Mr. Chairman, is that we would defer the construction year to 1993-94. In the meantime, we will carry the remainder of $400,000, which is $285,000, to 1992-93 and that would allow us to finish the design, and the construction will start in 1993-94. That was the reason for carrying over $285,000. We could not finish the design during this fiscal year. We are proposing that we carry over $285,000. We did decide that the building construction year be deferred to 1993-94, prior to going to the SCOF committee. Thank you.