Mr. Chairman, the conveyor system is very complicated and requires technical people to operate it. It has 16 independent conveyors which lead to the main conveyor belt. The cost associated with operating has been fairly large. We recognize that. We had anticipated initially to recover a good portion of this from CATSA. The amount of $222,000 is something we have been discussing with CATSA in terms of them compensating a portion of it. Our ask on this was $150,000. They have taken the approach that they will only fund $22,000 of it. This is based on their application of national policy. I believe that's what they call it. They are taking the same approach to all other airports. We are still negotiating this arrangement with CATSA. We are certainly not satisfied with the response to date. However, we have new additional costs for personnel, an electrician
and a millwright. I am not sure if we can combine the two. I don't know if our agreements will allow us to do that. There is an increase of power for $24,000; there are replacement parts; there is a contract with the manufacturer. That's what adds up to $222,000. We have to recognize that we have increased the footprint of this facility by 62 percent and that's really added to all our costs. Should we have forecasted this...We did an initial forecast. Unfortunately, we looked at facilities in other jurisdictions and tried to make our best evaluation. However, we always anticipated that we would negotiate this with CATSA, at least a good portion of it, and we haven't been able to make that come to a successful conclusion. We still are trying. However, the position they have taken has been fairly firm and we are not making a lot of headway.